>start 是测试原型的父级。当我折叠启动原型并展开测试原型的进度指示器时,未在高图甘特图中正确显示。
https://jsfiddle.net/bhagatch/nbchvupr/2/
series: [{
name: 'Project 1',
data: [{
id: 'start',
name: 'Start prototype',
start: Date.UTC(2014, 10, 18),
end: Date.UTC(2014, 10, 25),
completed: 0.25
}, {
id: 'test',
parent: 'start',
name: 'Test prototype',
start: Date.UTC(2014, 10, 27),
end: Date.UTC(2014, 10, 29),
completed: 0.35
}, {
name: 'Develop',
start: Date.UTC(2014, 10, 20),
end: Date.UTC(2014, 10, 25),
completed: {
amount: 0.12,
fill: '#fa0'
}
}, {
name: 'Run acceptance tests',
start: Date.UTC(2014, 10, 23),
end: Date.UTC(2014, 10, 26)
}]
}]
}(;
这是
Highcharts Gantt中的一个错误,报告如下: https://github.com/highcharts/highcharts/issues/10942
作为解决方法,您可以使用以下代码:
Highcharts.addEvent(Highcharts.Axis, 'afterBreaks', function() {
this.series.forEach(s => s.data.forEach(point => point.graphicOverlay = point.graphicOverlay && point.graphicOverlay.destroy()));
});
现场演示:https://jsfiddle.net/BlackLabel/o35pvhfn/