目前我有一些创建新任务的代码,但它确实有问题且不一致。
Public Sub Create_milestones()
proj = Globals.ThisAddIn.Application.ActiveProject
Dim myTask As MSProject.Task
Application.ScreenUpdating = False
For Each myTask In Application.ActiveSelection.Tasks
Application.SelectTaskField(Row:=1, Column:="Name")
Application.InsertTask()
Application.SetTaskField(Field:="Duration", Value:="0")
Application.SetTaskField(Field:="Start", Value:=myTask.Finish)
Application.SetTaskField(Field:="Name", Value:=myTask.Name & " - Milestone")
Application.SetTaskField(Field:="Resource Names", Value:=myTask.ResourceNames)
Application.SetTaskField(Field:="Text3", Value:="Milestone")
Application.GanttBarFormat(GanttStyle:=3, StartShape:=13, StartType:=0, StartColor:=255, MiddleShape:=0, MiddlePattern:=0, MiddleColor:=255, EndShape:=0, EndColor:=255, EndType:=0)
Application.SelectTaskField(Row:=1, Column:="Name")
Next
Application.SelectTaskField(Row:=-1, Column:="Name")
Application.SelectRow(Row:=0)
Application.RowDelete()
Application.ScreenUpdating = True
MsgBox("Done")
End Sub
在循环浏览所选任务时似乎走得太远了,并且创建的任务太多了,我通过返回并删除额外的任务来解决此问题,但这对我来说似乎不是最好的解决方案。
我意识到这段代码是 VB.net 但我也可以使用 VBA。
有没有更好的方法来创建和分配新任务的值?
可以通过存储所选任务的集合(或 .net 中的列表)然后循环访问这些任务来解决额外任务的问题。我将解决方案发布在 VBA 中,因为这可能是与其他查看者最相关的解决方案;如果需要,我可以发布 vb.net 版本。
Application.ScreenUpdating = False
Dim proj As Project
Set proj = Application.ActiveProject
Dim myTask As Task
Dim colTasks As New Collection
For Each myTask In Application.ActiveSelection.Tasks
colTasks.Add myTask, CStr(myTask.UniqueID)
Next myTask
Dim i As Object
For Each i In colTasks
Set myTask = ActiveProject.Tasks.UniqueID(i)
Dim newTask As Task
Set newTask = ActiveProject.Tasks.Add(myTask.Name & " - Milestone", myTask.ID + 1)
newTask.Duration = 0
newTask.Predecessors = myTask.ID & "FF"
newTask.Text3 = "Milestone"
newTask.ResourceNames = myTask.ResourceNames
Application.SelectRow newTask.ID, False
Application.GanttBarFormat GanttStyle:=3, StartShape:=13, StartType:=0, StartColor:=255, MiddleShape:=0, MiddlePattern:=0, MiddleColor:=255, EndShape:=0, EndColor:=255, EndType:=0
Next
Application.SelectRow colTasks(1), False
Application.SelectTaskField Row:=0, Column:="Name"
Application.ScreenUpdating = True
我更改了一些内容:1)与其对开始字段进行硬编码,不如使用任务关系在任务移动时将其与任务保持在一起;2)由于零持续时间任务没有工作,因此无需添加资源。
更新
这是 vb.net 版本:
Dim ProjApp As MSProject.Application = Globals.ThisAddIn.Application
ProjApp.ScreenUpdating = False
Dim proj As MSProject.Project = ProjApp.ActiveProject
Dim selTasks As New List(Of MSProject.Task)
For Each myTask As MSProject.Task In ProjApp.ActiveSelection.Tasks
selTasks.Add(myTask)
Next myTask
For Each myTask In selTasks
Dim newTask As MSProject.Task = proj.Tasks.Add(myTask.Name & " - Milestone", myTask.ID + 1)
newTask.Duration = 0
newTask.Predecessors = myTask.ID & "FF"
newTask.Text3 = "Milestone"
newTask.ResourceNames = myTask.ResourceNames
ProjApp.SelectRow(newTask.ID, False)
ProjApp.GanttBarFormat(GanttStyle:=3, StartShape:=13, StartType:=0, StartColor:=255, MiddleShape:=0, MiddlePattern:=0, MiddleColor:=255, EndShape:=0, EndColor:=255, EndType:=0)
Next
ProjApp.SelectRow(selTasks(0).ID, False)
ProjApp.SelectTaskField(Row:=0, Column:="Name")
ProjApp.ScreenUpdating = True